PriorityWho is in itWhat it means for an AI or cloud project
1
Protected needsConnected first
Homes, smaller businesses, defence, health, emergency services, and data centres tied to those functionsA critical or existing load can still be reserved. Draft orders put smaller businesses under 3 MW
2
Electrification and green projects
Transport, heat, industry, renewables, hydrogen and power-to-fuel plantsRanks above a commercial data centre
3
Storage
Batteries and extra storage on a shared siteCan be refused if it would displace a higher need
4
Certain large usersConnected last
Data centres, in principleAI and cloudWaits, and can be turned away
Draft priority order for new grid connections.