Merlin Edged’s Gigawatt-Scale Data Centre Plans in Spain

Merlin Edged’s Gigawatt-Scale Data Centre Plans in Spain
Takeaways
  • Merlin Properties and Edged Energy are behind four major Spanish data centre developments with approximately 3,100MW of combined long-term planned IT capacity.
  • Merlin’s current development programme covers 704MW across Spain and Portugal, but electricity supply difficulties have already forced it to pause two buildings at Arasur.
  • Spain’s new data centre decree introduces hourly renewable electricity matching requirements, with its future becoming an issue in the November 29 general election.

One of the largest planned data centres in Spain belongs neither to Amazon nor Microsoft. It is Merlin Edged’s proposed 1,400MW campus at Navalmoral de la Mata in Extremadura.

Merlin Properties, the Spanish-listed property group, is behind four of Spain’s largest planned data centre developments. Together, their long-term plans account for approximately 3,100MW of IT capacity.

But electricity supply is already holding back some of that expansion. Merlin has paused two buildings at its Arasur campus, and a decree the Spanish government approved on November 20, nine days before the general election, could add to the cost of its developments.

How Big Is Merlin Edged’s Data Centre Pipeline in Spain?

Merlin entered the data centre market in 2021 in partnership with US developer Edged Energy. Its four largest Spanish developments have approximately 3,100MW of potential IT capacity, including two gigawatt-scale campuses in Extremadura.

ProjectReference IT capacityStatus
Merlin Edged, Navalmoral de la Mata (Extremadura)1,400MWLong-term expansion option, under legal challenge
Merlin Edged, Valdecaballeros (Extremadura)1,000MWAnnounced
AWS, Aragón (quantified pipeline entries)894MWRegion operational, expansion under legal challenge
Microsoft, three campuses (Aragón)501MWPlanning
QTS (Blackstone), Calatorao (Aragón)432MWApprovals under legal challenge
Merlin Edged, Tres Cantos (Madrid)352MWFirst 30MW in development programme
Merlin Edged, Bilbao-Arasur (Álava)350MWPartly operational, later phases paused
XDC Properties, Altamira (Cantabria)320MWPlanned, power supply unresolved
Escatrón campus (Aragón)274MWRenewable self-consumption connection approved
Samca, Luceni (Aragón)216MWPermitting, under legal challenge

Its November 2026 trading update, however, puts the combined capacity of its three development phases across Spain and Portugal at 704MW, representing a planned investment of approximately €7.67 billion. That means Merlin’s larger campus figures include potential future expansions that are not yet part of its current investment programme.

The comparison uses planned and estimated IT capacity from property adviser Colliers’ March 2026 project tables, with development statuses updated to November 24. These figures include long-term expansion plans rather than just capacity committed for construction. AWS and Microsoft’s figures cover multiple developments.

As MRKT 3.0 previously reported in its analysis of Spain’s data centre market, Madrid leads in operational capacity while Aragón accounts for a substantial share of the future pipeline. Merlin’s long-term plans extend beyond these established markets.

What Are Merlin Edged’s Largest Data Centre Projects?

1. Merlin Edged, Navalmoral de la Mata (1,400MW)

Navalmoral is Merlin’s largest long-term data centre development opportunity. In May, the regional government opened its environmental permit application to public comment, putting the investment at €1.6 billion.

Merlin’s November trading update outlines an initial building with space for 100MW of IT capacity, of which 20MW would initially be equipped. The company identifies potential expansion to 1,400MW.

The development also faces a legal challenge. Extremadura’s High Court admitted a case in August brought by Ecologistas en Acción against its designation as a project of regional business interest.

2. Merlin Edged, Valdecaballeros (1,000MW)

Merlin announced this second Extremadura campus together with Navalmoral in January 2025.

It is at an earlier stage of development. Colliers gives no date for a first phase, and Valdecaballeros does not appear in Merlin’s current three-phase development programme.

3. Merlin Edged, Tres Cantos (352MW)

Tres Cantos, north of Madrid, is the largest planned development in the Madrid market identified in Colliers’ March report.

Urbanisation works are underway for the first 30MW building, with Merlin expecting a construction licence in the first quarter of 2027. Of that initial capacity, 20MW has already been booked, according to the company’s November trading update.

4. Merlin Edged, Bilbao-Arasur (350MW)

Arasur is Merlin’s most advanced large Spanish campus. The company reports 22MW of operational capacity, with two further 48MW buildings scheduled for delivery in December 2026 and December 2027.

Iberdrola will build a 126MW solar farm nearby to supply the campus.

However, Merlin has temporarily suspended development of buildings four and five over electricity supply difficulties. Delays affecting renewable energy projects planned by Solaria have contributed to the uncertainty, Data Center Dynamics reported on November 19.

How Does Merlin Compare With AWS and Microsoft?

Merlin has some of Spain’s largest long-term capacity plans, but Amazon Web Services (AWS) has a head start in Aragón.

AWS opened its Spanish cloud region in November 2022. In March 2026, it raised its planned investment in Spain to €33.7 billion.

Colliers’ March report identifies 894MW of quantified AWS pipeline entries in Aragón, with additional projects for which IT capacity has not been disclosed. Environmental groups have challenged the regional planning measures supporting parts of its expansion.

Microsoft plans three campuses in Aragón. Colliers estimates 167MW of IT capacity at each, giving a combined 501MW. These estimates measure the power available to computing equipment rather than the total electricity requirements cited in environmental filings.

Unlike the two US hyperscalers, which are expanding their own cloud infrastructure, Merlin also builds and leases data centre capacity to other cloud operators.

Who Are Merlin Edged’s Competitors in Spain?

Among Merlin’s competitors in the data centre development market is QTS, owned by Blackstone funds. Its planned campus at Calatorao has an estimated 432MW of IT capacity, according to Colliers.

In November, Blackstone acquired 150MW of grid connection capacity from Box2Bit, which dropped its own campus nearby. Aragón’s High Court has also admitted a challenge by Ecologistas en Acción against two regional government decisions concerning the Calatorao development.

XDC Properties, originally established by Stoneshield Capital, is behind the €3.6 billion Altamira campus near Santander. Colliers puts its planned IT capacity at 320MW, while engineering firm Sener describes the wider development as a 500MW project. The figures are not necessarily equivalent, as IT capacity excludes the electricity required by supporting infrastructure.

Altamira’s developers are also seeking the necessary electricity infrastructure.

Other large proposals include the Escatrón campus, for which Repsol is an energy partner, Grupo Samca’s development at Luceni and several projects from US company EdgeMode, whose future is uncertain following financial difficulties at the developer.

The admission of legal challenges against individual developments does not mean the courts have ruled against them.

Who Is Buying Merlin’s Data Centre Capacity?

At Getafe, Nebius, the Amsterdam-based AI cloud, signed for 18MW in July. CoreWeave also rents Merlin capacity in Barcelona. These AI clouds are among the customers seeking large blocks of computing capacity.

Merlin reported that its first 64MW of IT capacity was fully equipped and let in its November trading update. Across its wider data centre development programme, the company had secured leases for 160MW, with another 206MW in advanced negotiations and 68MW booked.

Its data centres generated €46.5 million in gross rental income in the first nine months of 2026, against €19.1 million in the same period a year earlier.

MRKT_Merlin_Ambitions_and_Programme

What Does Spain’s Data Centre Decree Mean for Merlin?

The decree ties new data centre connections to new renewable electricity generation.

The government approved Royal Decree 1032/2026 at an extraordinary cabinet meeting on November 20. It appeared in the official gazette the next day and entered into force on November 22.

The main energy requirements apply to data centres with at least 10MW of grid access capacity, including qualifying projects with existing connection permits that have not yet connected to the network.

Operators must generally match at least 80% of their electricity consumption with qualifying renewable generation on an hourly basis. Eligible facilities offering flexibility to the electricity system can follow a phased compliance schedule.

The decree also establishes energy efficiency, water sustainability and digital sovereignty requirements.

Before the final text was adopted, Merlin estimated that adapting its developments to the proposed regulations could require an additional €863m, primarily for battery energy storage.

That represents approximately 11% of its planned €7.67 billion investment. It remains to be seen how the final regulations will affect that calculation.

Can Merlin Deliver Its Gigawatt-Scale Plans?

The opposition People’s Party (PP) has promised to repeal the decree if it forms the next government, making data centre regulation an issue in the November 29 general election.

Unlike a royal decree-law, the royal decree does not require parliamentary validation. However, it implements requirements established under Royal Decree-Law 7/2026 of March 20. Replacing the November regulations would not necessarily remove those underlying obligations.

Electricity infrastructure remains a separate challenge. According to the decree’s preamble, Spain’s transmission system operator has granted more than 6GW of grid access capacity to data centres since December 2023.

“Six gigawatts granted, zero kilowatts connected,” Beatriz Corredor, chair of grid operator parent Redeia, said on November 10, referring to the difference between data centre access permits and actual connections.

Merlin’s Arasur pause illustrates that difference. Even if Spain’s next government changes the rules, the company still needs to secure the electricity to turn its gigawatt-scale plans into operating data centres.

Author: Akos Szima

See Also:

Where Is Spain Building Its Data Centres? Madrid Today, Aragón Tomorrow

Largest Data Centres in the World: The Gigawatt Club (2026)

The Biggest Data Centre Operators in the Nordics, Ranked (2026)

How We Checked This:

The capacity comparison draws on Colliers’ March 2026 Iberian data centre market report, particularly its project tables for Madrid, Aragón and other Spanish locations. IT capacity measures the power available to computing equipment, rather than the total electricity consumption of a facility. Where developers have not published IT capacity, Colliers uses estimates based on a reference power usage effectiveness (PUE) ratio of 1.5. The figures represent selected large developments and multi-site programmes, not an exhaustive national ranking. They include announced long-term expansion plans and should not be interpreted as committed or operational capacity.

Merlin’s current development programme and operational figures come from its November 2026 trading update. Project statuses have been updated using company disclosures, government publications and press coverage. The regulatory information comes from Spain’s Official State Gazette.

Frequently Asked Questions:

What is Merlin Edged?

Merlin Edged is a data centre development partnership between Spanish-listed property group Merlin Properties and US data centre infrastructure company Edged Energy.

Where is Merlin Edged building data centres in Spain?

Its four largest long-term Spanish developments are at Navalmoral de la Mata, Valdecaballeros, Tres Cantos and Bilbao-Arasur. Its wider portfolio includes facilities and developments in Getafe, Barcelona and Zaragoza.

What is Merlin Edged’s largest planned data centre?

Merlin Edged’s Navalmoral de la Mata campus in Extremadura has potential IT capacity of 1,400MW. The full capacity is not yet committed for construction.

How much data centre capacity is Merlin developing?

Merlin’s November 2026 trading update identifies 704MW across three development phases in Spain and Portugal, including 64MW already fully equipped and let. Its longer-term expansion ambitions extend beyond this programme.

Who uses Merlin Edged’s data centres?

Merlin’s data centre customers include AI cloud providers Nebius and CoreWeave, which have secured capacity at its facilities in Getafe and Barcelona respectively.