The 10 Biggest Neocloud Companies, Ranked by Power Actually Live

Neocloud Companies
Takeaways
  • CoreWeave is the biggest neocloud we rank, with 1.5GW of power running at the end of June 2026 and about 4.2GW under contract by August 11.
  • SpaceX reported 1.7GW of “nameplate compute” at September 30, more than CoreWeave. We leave it out because it does not say how much of that it rents to others.
  • Hut 8 has 949MW of AI capacity under contract and none of it live yet. Its first hall is due in the second quarter of 2027.

Last updated October 28, 2026; next update after the November results.

Neocloud companies rent out AI computing power, mostly on NVIDIA chips, outside the big three hyperscalers (Amazon, Microsoft and Google). CoreWeave is the biggest, with 1.5GW running, though SpaceX, which we do not rank, now reports more. Most have far more power signed than live: Hut 8 has 949MW under contract and none of it switched on yet.

NeocloudPower live / contracted
1. CoreWeave1.5GW / ~4.2GW
2. Crusoe (private)1GW / 6GW+ (gross, self-reported)
3. Core Scientific (landlord)437MW / ~1.1GW
4. Applied Digital (landlord)250MW / ~1.41GW
5. Nebius~170MW (Dec 2025) / 3.5GW+
6. Galaxy Digital (landlord)133MW / 526MW
7. TeraWulf (landlord)102MW / ~839MW
8. IREN~90MW / 200MW+
9. Nscale55MW / 1,370MW
10. Firmus (private)~46MW / 900MW+ (self-reported)
Latest figure each company had published by October 28, 2026. Most report IT load, the power that reaches the servers. A landlord leases buildings and power to others, who bring the chips. Download the full dataset with a source for every figure (CSV).

What Is a Neocloud?

A neocloud is a cloud company built mainly for AI work. It rents out racks of AI chips, often on multi-year contracts. The label now also covers the landlords that build the halls, many of them former bitcoin miners.

Which Neocloud Companies Are the Biggest?

CoreWeave leads by a wide margin on power that is actually running. Almost every company on the list has far more capacity signed than switched on.

Bar chart of neocloud power signed against power live: Crusoe 6GW+ signed and 1GW live, CoreWeave 4.2GW and 1.5GW, Nebius 3.5GW+ and 170MW, Applied Digital 1.41GW and 250MW, Nscale 1.37GW and 55MW, Hut 8 949MW signed and nothing live.

1. CoreWeave

The New Jersey company ended June with 1.5GW of active power, and its contracted power reached about 4.2GW by August 11. Its revenue backlog stood at about $104 billion, while one unnamed customer brought in 36% of second-quarter revenue.

2. Crusoe

Crusoe, which built the Abilene, Texas campus behind OpenAI’s Stargate, says it has 1GW of gross capacity running and more than 6GW contracted. In September, investors valued the private company at $30.9 billion.

3. Core Scientific

Once one of America’s biggest bitcoin miners, it was billing for 437MW by mid-July, mostly to CoreWeave. It has also leased about 530MW to AMD from 2027, so its total comes to about 1.1GW.

4. Applied Digital

The Dallas company brought Polaris Forge 1, its first North Dakota campus, to 250MW on October 1, leased to CoreWeave. Altogether, its leases across five campuses cover about 1.41GW and $36 billion of rent over their base terms.

5. Nebius

The Amsterdam company, formerly Yandex’s parent, reported about 170MW of active power at the end of 2025. Its letters to shareholders since then have not updated the figure. By May it had also contracted more than 3.5GW, led by Microsoft (about $17.4 billion) and Meta (up to $27 billion). On October 22 it added a $3.5 billion, 364-day secured facility from Citi.

6. Galaxy Digital

Galaxy delivered all 133MW of the first phase at its Helios campus in Texas, built as a bitcoin mine, to CoreWeave by June, its October 27 results confirmed. CoreWeave has leased 526MW there in total. Galaxy also has grid approval for another 830MW, which it calls Helios II, and no tenant for it yet.

7. TeraWulf

The bitcoin miner had switched on 102MW of AI capacity at Lake Mariner, New York, by July, against about 839MW contracted. That includes 401MW in Kentucky for Anthropic, which is not due until the second half of 2027.

8. IREN

The Sydney-founded miner runs its own AI cloud, with about 40MW live at the end of June. In August it added the first 50MW of four for Microsoft, under a $9.7 billion, five-year deal. The other three are due by the end of 2026. Bitcoin still brought in 49% of its revenue in April to June. Here is what IREN does, owns and owes.

9. Nscale

The London start-up listed 55MW live against 1,370MW contracted in its IPO filing. Its flagship site in Norway was running 6.4MW of a planned 30MW in October, six months late. Its biggest customers are Microsoft and Anthropic, with contracts worth up to $43.8 billion and $44.6 billion. Since the filing, Microsoft has pulled out of a planned 50MW site at Loughton, England.

10. Firmus

The Australian company had about 46MW running when it pulled its stock market listing on October 9 after weak investor demand. It says it has more than 900MW under contract, with OpenAI as an anchor customer.

Not ranked: SpaceX, with more computing power than CoreWeave

SpaceX reported 1.7GW of “nameplate compute” on September 30, up from 1.4GW at the end of June. That is more than CoreWeave’s 1.5GW, though the two count capacity differently and SpaceX also uses the capacity for its own Grok models. Its Super Intelligence unit, which covers cloud services, Grok, Cursor and advertising, made $7.6 billion of SpaceX’s $14.6 billion third-quarter revenue.

It also rents capacity to others: Anthropic’s IPO filing lists commitments of up to $120.5 billion to SpaceX through 2029, though either side can end the deals on 90 days’ notice from early 2027. Short seller Jim Chanos wrote on X on October 16 that SpaceX is “actually the largest global neocloud, starting in 2027”. We leave it out of the ranking because SpaceX does not say how much of its capacity it rents out. Counted in full, it would rank first.

Not ranked: Hut 8, with nothing live

Hut 8 has 949MW of AI capacity under contract and none of it live, more than Galaxy or TeraWulf has signed. Its first hall at River Bend, Louisiana, leased to Fluidstack, is due in the second quarter of 2027. Research firm SemiAnalysis has traced the tenant at its Beacon Point campus in Texas to NVIDIA, which passes the space to Lambda for Anthropic.

Just below the cut sit WhiteFiber, with up to 40MW, and Riot Platforms, with 25MW running for AMD and 241MW contracted. Fluidstack, founded in Oxford, and Lambda, which is raising up to $4 billion before a planned listing, don’t publish live capacity. AMP, Anjney Midha’s investment firm, has started selling computing power too.

Can You Invest in Neocloud Companies?

Most of the companies on the list already trade publicly. CoreWeave, Nebius, IREN, Applied Digital, Core Scientific, Galaxy Digital, TeraWulf and Hut 8 all list on Nasdaq. Crusoe, Firmus, Fluidstack and Lambda remain private, while Nscale has filed to list in New York as NSCL. Our IPO tracker follows every neocloud listing and filing.

Roundhill launched the first neocloud ETF on August 6. Its definition includes companies moving “from cryptocurrency mining or blockchain operations to AI and HPC data center operations”. Miners appeal because their sites already have big grid connections, which new data centres often wait years to get.

Seven of its ten largest holdings on September 30 mine bitcoin or used to. They are IREN, Hut 8, Galaxy, TeraWulf, Riot Platforms, Cipher Digital and Core Scientific. By weight, though, Nebius and CoreWeave make up about 61% of the fund. Roundhill’s own pitch on X in August conceded that “most of that power isn’t online yet”.

Short sellers are betting the gap will hurt. Data firm S3 Partners tracks six of the listed landlords, including Hut 8 and TeraWulf. Their median short interest rose from 18.5% of tradable shares in July to 22% in mid-October.

Who Pays for All This Capacity?

A handful of buyers account for most of the contracted power.

  • Microsoft has deals with CoreWeave, Nebius, IREN, Nscale and Lambda, and Meta with Nebius and CoreWeave.
  • Anthropic is building with Fluidstack, TeraWulf and Nscale, and its IPO filing also shows contracts with Lambda (about $41.3 billion) and SpaceX.
  • Google guarantees part of Fluidstack’s rent at TeraWulf, Cipher and Hut 8.

When one buyer moves, the contracted column moves too. Microsoft dropped its plans for Nscale’s Monarch site, and Anthropic has since signed for 460MW there.

The gap matters because rent and chip fees mostly start when capacity goes live. Until then the contracts pay little, while the debt costs interest. CoreWeave carried about $35 billion of debt at the end of June, plus about $16.5 billion of lease obligations, before selling more convertible bonds in September. In mid-October its shares fell more than 15% in a day. On October 20, the yield on its 2031 bonds stood at about 15.6%, a level that usually signals distress. Nebius had $8.5 billion and then raised $5.75 billion more in August, and IREN, Hut 8 and Applied Digital each owe between $6 billion and $8 billion. Even in Europe, most of the money comes from American investors and tech giants.

TeraWulf’s chief executive, Paul Prager, set out the test operators now face on October 15.

What Did Elon Musk Say About Neoclouds?

Elon Musk said most of them will fail or be swallowed up. On October 25 he wrote on X that debt markets have “almost entirely shut off access to money for any company that doesn’t have substantial revenue independent of AI data centers”. “That means the 200+ neoclouds are going to see guppy-level death and consolidation,” he added. “Some will make it through, but not many.” Asked whether he was talking the stocks down ahead of a buyout, he replied: “SpaceX is not buying any neoclouds. Pointless.”

Research firm Gartner made a similar forecast on October 14. By 2030, it expects “cost pressure and a lack of a differentiating business model” to force more than 80% of neocloud providers to “cease independent operations”.

TeraWulf’s Paul Prager replied on X to an earlier Musk post about “stranded compute”: Musk “may be right that we’ll see unfinished data centers”, he wrote, but “we don’t build on spec”.

Crusoe’s Chase Lochmiller told the Bloomberg Invest conference on October 27 that “a lot of this angst is overblown”, defending CoreWeave after its share slide without mentioning Musk.

When Do Neocloud Companies Report Next?

Hut 8 goes first, on November 4, and CoreWeave reports on November 10.

CompanyNext results (New York time)
Hut 8November 4, call at 8:30am
Core ScientificNovember 5, call at 8:30am
IRENNovember 5, call at 5pm (its fiscal first quarter)
TeraWulfNovember 6, call at 8am
CoreWeaveNovember 10, call at 5pm
NebiusDate not announced yet
Applied DigitalNot announced; last reported on October 7
Galaxy DigitalReported its third quarter on October 27

Author: Akos Szima

See Also:

Nscale IPO: $103 Billion of Contracts, Only 55MW Live

Is Nscale Really European Sovereign AI? The $14.6bn Question

Europe Is Hosting an AI Build-Out It Cannot Afford to Fund

What Is Nebius? The AI Cloud Now Worth More Than CoreWeave

How We Checked This:

We took live and contracted power from each company’s latest filing or results published by October 28, 2026, or its own announcements if private. Companies measure power differently, so treat the ranking as a guide. IREN’s live figure, Nscale’s contracted total and the debt totals are our sums.

Change log: October 28, 2026: added SpaceX, Elon Musk’s warning, the results calendar and the latest company news; no ranked figure changed. October 16, 2026: first published.

Frequently Asked Questions:

What are the top 5 neoclouds?

CoreWeave is the biggest we rank, with 1.5GW running at the end of June 2026. Next come Crusoe (1GW, self-reported), Core Scientific (437MW), Applied Digital (250MW) and Nebius (about 170MW), on each company’s latest published figures.

Is there a neocloud ETF?

Yes. Roundhill launched the Neocloud ETF (NCLD) on August 6, 2026. Nebius and CoreWeave make up about 61% of it, and seven of its ten largest holdings mine bitcoin or used to.

Which neoclouds are European?

Nebius, based in Amsterdam, and Nscale, based in London, are the largest. Fluidstack was founded in Oxford.